Chandni Chowk Underground Wiring Project Aims for Safer, More Reliable Power

Chandni Chowk Underground Wiring Project Aims for Safer, More Reliable Power.webp

New Delhi, February 26 The Delhi government is enhancing the city's power infrastructure for the next 50 years, Chief Minister Rekha Gupta said on Wednesday after inaugurating a project to move overhead electricity wires underground in Chandni Chowk.

Addressing the gathering, Gupta said that 28 roads and streets in Old Delhi, including Kucha Mahajani, Bhagirath Palace, Jama Masjid Road, and Nai Sadak, will be freed from hanging electricity cables. The project will cost Rs 160 crore.

The work will be carried out in phases during the night to minimize disruption to daily life and traffic, a statement issued by the chief minister's office (CMO) said.

Around 10,000 consumers will directly benefit from the project, which will reduce fire hazards and weather-related power disruptions, improve supply reliability, and significantly beautify the historic area, the statement said.

According to Gupta, the government is promoting the adoption of electric vehicles, which will directly impact the need for more power.

The chief minister said the government will also restore the historic Town Hall building as a monument.

A total of 52.5 km of overhead wiring in Chandni Chowk will be moved underground to enhance safety and reliability while preserving the area's heritage character, officials said.

The chief minister also laid the foundation for BYPL's 66/11 KV, 63 MVA gas-insulated switchgear (GIS) indoor grid at Mandoli, and four standalone utility-scale battery energy storage systems (BESS) across south and west Delhi.

Officials said a digital twin-enabled system will introduce real-time intelligence and predictive monitoring to Old Delhi's modernized power network.

The Mandoli GIS indoor grid, to be constructed for Rs 55.5 crore, will strengthen the power backbone of north-east Delhi and benefit nearly 1.5 lakh consumers, the statement said. It is targeted to be completed within 18 months.

The residents of Mandoli, Harsh Vihar, Bank Colony and adjoining areas will receive a more stable and reliable electricity supply, it said.

The Rajiv Gandhi Super Speciality Hospital, Mandoli Jail, and a DTC EV bus depot will also receive assured power, the statement added.

The BESS project by BSES Rajdhani Power Limited (BRPL) will have a total capacity of 55.5 MW and will benefit around 50,000 consumers in Shivalik, 1,28,000 in Dwarka (G-5), 16,000 in Dwarka (G-7), and 28,000 consumers in Goyla Khurd with seamless supply, according to the statement.

All projects are targeted for commissioning before March 2027.

The statement said the battery systems will help reduce peak-hour load shedding, improve voltage stability, and strengthen the grid, adding that the technology is environmentally sustainable and supports the transition to clean energy.
 
Tags Tags
battery energy storage systems chandni chowk delhi government dwarka electric vehicles electricity distribution fire hazards gis (gas insulated switchgear) goyla khurd mandoli mandoli jail overhead electrical wiring power infrastructure rajiv gandhi super speciality hospital shivalik underground cables